Independent power producer (IPP), Edra Power Holdings Sdn Bhd, is on track to build its pilot large-scale solar photovoltaic plant in Kedah by early 2018, with a generating capacity of 50 MWac.
Project Kedah Solar, which will bring immense economic spillover benefits to the state, would be undertaken by Edra's wholly-owned unit, Edra Solar Sdn Bhd.
"The Kedah solar plant is expected to generate approximately 80,000 megawatt hours (MWh) of electricity per year and would be developed over 104 hectares at Bandar Kuala Ketil in Baling, Kedah," Datuk Mark Ling, President and Executive Director of Edra Power, told Bernama today.
He said the development of the solar plant would turn the once agricultural land in Kuala Ketil into an industrial site, thus creating a significant positive impact on the State's economic growth.
Project Kedah Solar would be the first of multiple-utility scale solar photovoltaic power plant with an aggregate capacity of up to 500 megawatts to be developed by Edra pursuant to the conditional award from the Ministry of Energy, Green Technology and Water.
Edra Solar had entered into a land sales and purchase (SPA) agreement in August 2015 with BDB Land Sdn Bhd, a subsidiary of Bina Darulaman Bhd (BDB) for the acquisition of the said land parcel.
As a Malaysian-based power producer, Edra said, it is committed to develop the local power sector, including the renewable energy sector.
To this end, he said, Edra would maximise local Malaysian content and create skilled jobs for Malaysians through Project Kedah Solar during the construction, operations and maintenance of the project, with engineers, operational and management team comprise predominantly local staff.
Given its significance, Ling said, the Kedah State Government has extended its strong support and cooperation towards the smooth implementation of the project.
The relevant agencies and authorities in the state have granted the necessary approvals to enable Edra Solar to proceed with the project.
Conditions precedent to the SPA have been fulfilled and Edra Solar has been granted vacant possession by BDB Land for it to proceed with site works.
Edra Solar has also already obtained the full planning approval from Baling District Council to commence site works, he said.
The clean solar electricity will avoid 36,000 tons of carbon emissions per year, thereby supporting the government's initiative to reduce the generation of greenhouse gases, he said.
Going forward, he said, Edra hopes to explore further working collaborations with BDB and Kedah in identifying potential sites from its current and future landbank, for development of new solar farms in the state that will help contribute towards the government's green programme.
Edra is one of South-East Asia's leading IPPs, controlling a diversified portfolio of quality power generation assets across a range of technologies.
The group has a portfolio of 13 power and desalination plants in Malaysia, Egypt, Bangladesh, Pakistan and the United Arab Emirates, with a total net generating capacity of 5,529 MW and a water desalination capacity of 16 million imperial gallons per day.
Edra is the second largest IPP in Malaysia and Bangladesh and is the largest IPP group operating in Egypt.
Edra is a wholly-owned subsidiary of China General Nuclear Power Corp, which is a leading nuclear energy company in the world with investments in more than 25-gigawatt clean and renewable energy projects, including wind, solar, hydro, gas-fired, efficient coal-fired and fuel-cell powered projects in China, South Korea, Singapore, UK, France and Australia.
-- BERNAMA
Bernama
Sun Mar 19 2017
He said the Kedah solar plant is expected to generate approximately 80,000 megawatt hours (MWh) of electricity per year.
Mesyuarat perundingan Enam Pihak Arab bincangkan perkembangan di Gaza
Mesyuarat perundingan Jawatankuasa Enam Pihak Arab itu membincangkan perkembangan serangan Israel ke atas Semenanjung Gaza.
Chegubard didakwa di Mahkamah Sesyen KL esok - Peguam
Badrul Hisham Shaharin atau dikenali Chegubard akan didakwa di Mahkamah Sesyen Kuala Lumpur esok atas pertuduhan memfitnah dan menghasut.
Pulau Pinang, kerajaan pusat bekerjasama tarik pelaburan semikonduktor
Kerajaan Pulau Pinang akan bekerjasama dengan Kerajaan Persekutuan untuk meneruskan usaha menarik pelaburan dalam sektor semikonduktor, termasuk segmen reka bentuk litar bersepadu (IC) di negeri itu.
Rakyat Malaysia di Jordan jadi duta produk PMKS negara
Menteri Pembangunan Usahawan dan Koperasi Datuk Ewon Benedick menyarankan rakyat Malaysia yang menetap di Jordan supaya memainkan peranan sebagai “duta” untuk mempromosikan produk perusahaan mikro kecil dan sederhana (PMKS) SERTA koperasi negara.
Mohamed Khaled tiba di Indonesia, dijadual bertemu Prabowo
Menteri Pertahanan Datuk Seri Mohamed Khaled Nordin tiba di Jakarta hari ini untuk lawatan kerja rasmi sulung beliau ke Indonesia sejak memegang jawatan itu.
SPRM mohon maklumat dari Jerman
Suruhanjaya Pencegahan Rasuah Malaysia (SPRM) memohon maklumat terkini daripada pihak berkuasa Jerman mengenai dana bon 1Malaysia Development Berhad (1MDB) yang dipercayai digunakan untuk membeli kereta mewah di negara itu pada 26 Okt 2022.
SPRM siasat pemimpin kanan di utara tanah air
Seorang pemimpin kanan di utara tanah air disiasat Suruhanjaya Pencegahan Rasuah Malaysia (SPRM) kerana disyaki melantik beberapa syarikat yang mempunyai kepentingan dengannya membabitkan beberapa projek pembekalan melibatkan peruntukan kira-kira RM300,000.
Kembangkan kandungan tempatan melalui AI
Menurut Setiausaha Agung Organisasi Kerjasama Digital (DCO) Deemah Al Yahya, terdapat 2.7 peratus daripada penduduk dunia tidak berhubung malah tidak mempunyai sambungan asas internet. Beliau turut berkata infrastruktur pengkomputeran setiap negara perlu mempunyai kemampuan untuk mengembangkan kandungan tempatan khususnya yang melibatkan penggunaan AI.
AI tidak dapat ganti guru
Menteri Pendidikan Rwanda, Gaspard Twagirayezu berkata kepesatan teknologi AI dalam pendidikan tidak dapat menggantikan guru malah membantu guru dalam menyediakan bahan pengajaran yang bermanfaat kepada pelajar.
Berita tempatan pilihan sepanjang hari ini
Berikut adalah berita yang paling menjadi tumpuan sepanjang Ahad, 28 April 2024.
Edra bina loji tenaga solar bernilai RM400 juta di Kedah
Pelaburan terbesar di Kedah bakal menjadi kenyataan dengan loji tenaga solar bernilai RM400 juta oleh Edra Power Holdings Sdn Bhd.