KUALA LUMPUR: The Mass Rapid Transit (MRT) Putrajaya Phase One line is still undergoing some rectification by the turnkey operator in preparation for full operations, said MRT Corporation Sdn Bhd.
On Nov 16, 2021, MRT Corp chief executive officer Datuk Mohd Zarif Hashim said the line may be ready for revenue service in the second quarter (Q2) of 2022.
Prior to the announcement, MRT Corp had postponed the opening date for MRT Putrajaya Line Phase One from August to mid-November 2021.
The trial operations for Phase One has been ongoing since April 29, 2021.
A total of 16 trains have been running between Kwasa Damansara MRT Station and Kampung Batu MRT Station in full-service mode -- minus the passengers -- to stimulate actual operations.
The MRT Putrajaya Line (formerly known as the Sungai Buloh-Serdang-Putrajaya Line) runs through 56.2 kilometres and has 36 stations for Phases One and Two, starting from the Kwasa Damansara station to Putrajaya.
"Meanwhile, the construction of the MRT Putrajaya Line Phase Two is also progressing well," MRT Corp told Bernama via email.
As of Oct 4, 2021, the construction of Phase Two line is 93.52 per cent completed, and it is expected to begin operations in January 2023.
-- BERNAMA
Bernama
Fri Jan 21 2022
The MRT Putrajaya Line (formerly known as the Sungai Buloh-Serdang-Putrajaya Line) runs through 56.2 kilometres and has 36 stations for Phases One and Two, starting from the Kwasa Damansara station to Putrajaya. - BERNAMA
Angka kematian lebuh raya runtuh di China meningkat kepada 36
Angka kematian akibat sebahagian lebuh raya di wilayah Guangdong, selatan China runtuh meningkat kepada 36 orang, kata pihak berkuasa tempatan, lapor Xinhua.
PRK Kuala Kubu Baharu: Tular pula isu hutang, calon PN enggan jawab
Calon PN bagi PRK Kuala Kubu Bharu, Khairul Azhari Saut sekali lagi terpalit dakwaan hutang melibatkan perkhidmatan kredit komuniti.
Bursa Malaysia dibuka rendah
Pada 9.05 pagi, FTSE Bursa Malaysia KLCI (FBM KLCI) merosot 1.21 mata kepada 1,574.76 daripada 1,575.97 pada Selasa.
UUM dan tiga wilayah di Selatan Thailand rintis kerjasama pendidikan tinggi
Kerjasama yang diberi keutamaan ialah latihan perguruan dan kursus berkaitan bahasa Inggeris bagi pelajar dan tenaga pengajar.
Perkembangan terkini Jelajah Microsoft Build: AI Day
Acara sehari secara percuma yang direka untuk membantu pembangun meneroka peluang baharu dengan kecerdasan buatan (AI) serta memajukan kemahiran mereka dengan AI dan Microsoft Azure.
[TERKINI] Siti Bainun dihukum penjara 12 tahun
Pengasas Rumah Bonda, Siti Bainun Ahd Razali dihukum penjara 12 tahun oleh Mahkamah Tinggi pada khamis, atas dua pertuduhan mengabai dan menganiaya remaja perempuan sindrom down, yang juga dikenali dengan nama Bella, tiga tahun lalu.
Harus renjis, bilas kenderaan dengan air ruqyah - Mufti
Perbuatan tersebut bukanlah satu amalan yang khurafat dan tidak bertentangan dengan syariat.
WEF: Emerging economies: How to fix the debt problem?
Papagomo didakwa hasut, datangkan kebencian terhadap Agong
Wan Muhammad Azri didakwa menerbitkan penerbitan menghasut berkaitan isu pemilik KK Supermart menghadap Sultan Ibrahim di laman X miliknya.
Siti Bainun kekal bersalah abai, aniaya Bella
Hakim, Datuk Noorin Badaruddin memutuskan demikian selepas menolak rayuan Siti Bainun.
Pemaju, kontraktor, pengilang di Johor diarah selesai isu penempatan pekerja asing
Kerajaan Johor mengarahkan pemaju dan kontraktor serta pengilang di seluruh negeri itu, untuk menyelesaikan isu penempatan pekerja asing.
MRT3 : Proses pengambilalihan tanah secara berperingkat tahun depan
MRT Corp akan memulakan proses pengambilan tanah secara berperingkat mulai 2024 bagi Projek Laluan Lingkaran Transit Aliran Massa 3 (MRT3) yang dijangka mengambil masa dua tahun untuk dimuktamad.
Kajian LRT Pulau Pinang oleh MRT Corp dijangka siap awal 2024
DUN Pulau Pinang diberitahu MRT Corp telah menawarkan tender untuk pelantikan perunding bagi membuat kajian berkenaan projek LRT di negeri itu.
Tahap kemajuan RTS Link capai 52 peratus setakat Oktober
Projek pembinaan Sistem Transit Rapid (RTS) Link Johor Bahru-Singapura yang melintasi Selat Johor kini mencapai kemajuan 52 peratus siap dan berjalan mengikut jadual ditetapkan.
MRT Corp kaji bina LRT Pulau Pinang bawah tanah, laut - Chow
MRT Corp akan membuat kajian kebolehlaksanaan untuk melihat kesesuaian pembinaan projek itu di bawah tanah untuk jajaran yang terletak di tengah bandar serta bawah laut.
Al-Salam REIT, MRT Corp meterai MoU bina jejantas bernilai sehingga RM15 juta
Jejantas berhawa dingin sepanjang 42 meter menghubungkan Komtar JBCC dengan jambatan terancang stesen Sistem Transit Rapid (RTS) Link Bukit Chagar itu akan dibuka pada 2027.
Fasa pertama projek LRT Pulau Pinang bermula hujung tahun ini - Loke
Pelaksanaan fasa pertama projek Transit Aliran Ringan (LRT) di Pulau Pinang dijangka akan dimulakan penghujung tahun ini.
Bashir Ahmad dilantik Pengerusi MRT Corp
Mass Rapid Transit Corporation Sdn Bhd (MRT Corp) melantik Tan Sri Bashir Ahmad Abdul Majid sebagai pengerusinya berkuat kuasa 3 April 2023.
Pembukaan MRT laluan Putrajaya perkukuh sistem pengangkutan awam negara
Sistem pengangkutan awam negara terus diperkukuh apabila perkhidmatan Transit Aliran Massa (MRT) laluan Putrajaya beroperasi sepenuhnya pada 16 Mac ini.
MRT2 mula beroperasi 16 Mac ini - Anthony Loke
Transit Aliran Massa Laluan Putrajaya Fasa Dua (MRT2) akan mula beroperasi pada 16 Mac ini, demikian diumumkan oleh Menteri Pengangkutan, Anthony Loke.