KUALA LUMPUR: The Public Accounts Committee (PAC) requested that the Cabinet make some important decisions at the upcoming Cabinet Meeting, following the declassification of a forensic audit report related to the Littoral Combat Ship (LCS) programme.
PAC chairman Wong Kah Woh in a statement requested that further forensic auditing be carried out by Boustead Heavy Industries Corporation Bhd (BHIC) on the LCS project to cover all transactions and activities related to the implementation of the project and the Letter of Award (LOA) from 2015 to date.
"Although most of the LOAs were issued by Boustead Naval Shipyard Sdn Bhd (BNS) during that period, the implementation was at least until 2018.
"The report found that as long as all transactions and activities related to its execution until 2018 have not been thoroughly investigated, it is likely that important facts for proving criminal behavior will be left out," he said.
In addition, he said the report of the Governance, Procurement and Finance Investigation Committee (JKSTUPKK) regarding six New Generation Patrol Vessels (NGPV), Integrated Logistics Support and Commercial Package Program by the Royal Malaysian Navy (TLDM) should also be declassified.
He said this was in view of BNS' use of funds allocated for the LCS for the payment of the NGPV's bad debts.
-- BERNAMA
Bernama
Tue Aug 23 2022
PAC Chairman Wong Kah Woh Wong requested that further forensic auditing be carried out by Boustead Heavy Industries Corporation Bhd on the LCS project. - BERNAMA
Pusat dialisis Perkeso di Pulau Pinang hujung tahun ini
Pertubuhan Keselamatan Sosial (Perkeso) bakal membuka sebuah pusat dialisis di Pulau Pinang menjelang hujung tahun ini, kata Menteri Sumber Manusia Steven Sim Chee Keong.
RISDA usaha selesaikan 12,385 hektar kebun getah tidak bertoreh tahun ini
Hal ini bertujuan untuk memajukan semula sektor itu, selain membantu penoreh getah meningkatkan pendapatan mereka.
AWANI Ringkas: Ada usaha kurangkan majoriti
Ikuti rangkuman berita utama yang menjadi tumpuan sepanjang hari di Astro AWANI menerusi AWANI Ringkas.
Separuh akhir Piala Thomas: Leong Jun Hao pamer semangat juang tinggi sebelum tewas
Perseorangan lelaki negara, Leong Jun Hao, mempamerkan semangat juang tinggi walaupun tewas kepada pemain tuan rumah, Li Shi Feng, dalam separuh akhir Piala Thomas di Chengdu sebentar tadi.
Pulau Pinang umum pelan untuk Taman Reka Bentuk IC dan digital
Kerajaan negeri Pulau Pinang mengumumkan pelannya untuk mewujudkan Taman Reka Bentuk Litar Bersepadu (IC) dan Digital.
PM Anwar hadir Mesyuarat Pembangunan Kedah
Perdana Menteri Datuk Seri Anwar Ibrahim hari ini menghadiri Mesyuarat Khas Pembangunan Negeri Kedah di Wisma Darul Aman.
Piala Thomas: Gegaran sambutan tayangan skrin besar
Bersama Wartawan Astro AWANI, Ridauddin Daud di Putrajaya, Dataran Putrajaya, membuat liputan gegaran sambutan tayangan skrin besar Separuh Akhir Piala Thomas.
Polis tahan 28 lelaki bergaduh di Butterworth
Polis menahan 28 lelaki hari ini, dipercayai terlibat dalam satu pergaduhan membabitkan dua kumpulan di Jalan Raja Uda di Butterworth pada Jumaat, seperti yang tular melalui media sosial.
KPDN terima 15,753 aduan pengguna setakat April - Fuziah
Sebanyak 15,753 aduan kepenggunaan diterima di seluruh negara, termasuk 7,711 aduan menerusi platform Aduan Suri KPDN.
Laporan cuaca melampau dan bencana negara
Cuaca panas di kawasan berikut: Padang Terap, Pasir Mas, Jeli, Kota Bharu, Pasir Puteh, Tanah Merah, Besut, Setiu, Kuala Krai, Kota Marudu.
Tahap 1, tahap berjaga-jaga, suhu 35 hingga 37 darjah celsius untuk sekurang-kurangnya tiga hari.
Banjir di Johor, Kota Tinggi, 1 PPS, 22 keluarga, 88 mangsa.
Tahap 1, tahap berjaga-jaga, suhu 35 hingga 37 darjah celsius untuk sekurang-kurangnya tiga hari.
Banjir di Johor, Kota Tinggi, 1 PPS, 22 keluarga, 88 mangsa.
SPRM tidak pernah henti siasatan kes LCS - Azam Baki
Suruhanjaya Pencegahan Rasuah Malaysia (SPRM) tidak pernah menghentikan siasatan berhubung kes pembinaan Kapal Tempur Pesisir (LCS).
Perolehan kumpulan kedua tiga LMS dijangka dimuktamadkan tahun ini - Khaled
Mohamed Khaled berkata pembinaan LMS dijangka mengambil masa tiga tahun selepas proses perolehan tersebut selesai.
LCS: RM7.02 bilion telah dibayar kerajaan sehingga kini - Menteri Pertahanan
Angka itu merupakan 62.49% daripada jumlah kos projek berjumlah RM11.22 bilion, dibayar mengikut kontrak yang ditetapkan.
LCS pertama capai 85 peratus November ini, lalui ujian di laut
Kedua-dua ujian berkenaan mengambil masa selama dua tahun sebelum LCS pertama dijangka ditauliah pada 2026.
Projek LCS: Representasi bekas Pengarah Urusan BNS untuk gugur pertuduhan ditolak
Jabatan Peguam Negara menolak representasi Tan Sri Ahmad Ramli Mohd Nor untuk menggugurkan tiga pertuduhan pecah amanah.
LCS: Mindef sedia bentang laporan setiap tiga bulan - Adly
Mindef akur dengan syor penambahbaikan PAC untuk membentangkan laporan kemajuan Projek Pembangunan Kapal Peronda Generasi Kedua (LCS) setiap tiga bulan.
Kenaikan kos RM2.068 bilion LCS ambil kira penjimatan RM450 juta secara keseluruhan - PAC
Bahagian Audit Kementerian Pertahanan telah melaksanakan satu semakan terperinci bagi mengesahkan nilai kos tambahan tersebut.
Isu LCS: Mindef nafi tak libat AGC, tiada kemajuan pembinaan
Kementerian Pertahanan menegaskan AGC sentiasa dilibatkan dalam memuktamadkan perjanjian tambahan keenam (SA6) berkenaan pembinaan LCS.
Lanjut lagi, PAC dedah 5 kapal tempur LCS hanya akan siap pada 2029
Tempoh masa bagi pembinaan lima Kapal Tempur Pesisir (LCS) akan dilanjutkan lagi kepada 83 bulan dan kesemua lima kapal berkenaan akan diperoleh Tentera Laut Diraja Malaysia (TLDM) pada 2029.
Kemajuan LCS antara 4 laporan dibentang pada Mesyuarat Ketiga Dewan Rakyat Oktober ini
Laporan Kemajuan Projek Pembinaan Kapal Peronda Generasi Kedua - Kapal Tempur Pesisir (LCS) adalah antara empat laporan yang akan dibentangkan pada Mesyuarat Ketiga Dewan Rakyat, Oktober ini.