BEIJING: The land acquisition process for the 665-kilometre-long East Coast Rail Link (ECRL) project is now 93 per cent completed, said Railway Business Unit of China Harbour Engineering Company Ltd (CHEC), general manager Zhang Wenfeng.
He said the seven per cent incomplete part involved Section C of the rail alignment, which is in Selangor.
"The seven per cent is not a big amount, however, if there is a delay (in land acquisition), it will affect the completion time. Otherwise, the project can be completed on time," he told Malaysian reporters in a special interview recently.
CHEC is a subsidiary of China Communications Construction Company Ltd (CCCC), the main contractor of the ECRL project.
Zhang said the construction of the project has achieved 50.29 per cent progress till the middle of last month and is on track to be completed by the end of 2027.
"The project is divided into three sections, A, B and C. We have finished most of the civil work in sections A and B, roughly this project is half finished," he added.
He said the project is expected to provide up to 18,000 job opportunities for the local people.
The implementation of the project will also see more than 5,000 technicians trained in railway construction and operation, he added.
Zhang said they have also implemented environmental protection including changing the design of the alignment and adopting advanced TBM (Tunnel Boring Machine) equipment to replace the traditional mining methods such as blasting and excavation for tunnel construction to minimise the impact of the project on the environment.
He said the project could stimulate economic development and is very crucial to improving connectivity between Peninsular Malaysia's East Coast states and the West Coast States.
The project which is also a key part of China's Belt and Road Initiative (BRI) in Malaysia will also strengthen bilateral relations between both countries.
ECRL is a proposed railway infrastructure project designed to improve connectivity between Peninsular Malaysia's East Coast states (Kelantan, Terengganu, and Pahang) and the West Coast states (Negeri Sembilan, Selangor, and the Federal Territory of Putrajaya), which is currently only partially connected by rail.
-- BERNAMA
Bernama
Mon Sep 18 2023
The project, which is also a key part of China's Belt and Road Initiative (BRI) in Malaysia, will also strengthen bilateral relations between both countries. - BERNAMA/Filepic
PRK Kuala Kubu Baharu: Ramasamy perlu bertanggungjawab jika pengundi pilih pemimpin tidak tepat - Ramanan
Jika kempen tolak undi PH itu berjaya, Ramasamy perlu berdepan penduduk Kuala Kubu Baharu sekiranya timbul masalah pada masa hadapan.
Jiwa SME: Permintaan daun moringa meningkat, jadi tumpuan luar negara
Berdasarkan laporan Vodus Market Research, sebuah firma penyelidikan dan analisis data pasaran dalam talian, kira-kira 71 peratus penduduk di negara ini mengambil suplemen pada 2021.
Nilai pasaran suplemen negara juga menunjukkan peningkatan ketara dalam tempoh 2014 hingga 2019, iaitu daripada RM2.07 bilion kepada RM3.1 bilion. Angka itu dijangka terus meningkat pada masa akan datang.
Nilai pasaran suplemen negara juga menunjukkan peningkatan ketara dalam tempoh 2014 hingga 2019, iaitu daripada RM2.07 bilion kepada RM3.1 bilion. Angka itu dijangka terus meningkat pada masa akan datang.
Biden kekal tidak sokong pencerobohan di Rafah
Mesej itu disampaikan menerusi perbualan telefon dengan Perdana Menteri Israel, Benjamin Netanyahu pada Ahad.
Biden kekal tidak sokong pencerobohan di Rafah
Presiden Amerika Syarikat, Joe Biden bercakap dengan Perdana Menteri Israel, Benjamin Netanyahu, pada Ahad.
Tiga perkara perlu dilakukan bagi elak kemusnahan di Gaza
Presiden Palestin Mahmoud Abbas menyuarakan tiga perkara yang perlu diberikan pertimbangan masyarakat dunia dan mengiktiraf Palestin sebagai negara merdeka termasuk ahli penuh Persatuan Bangsa Bangsa Bersatu (PBB). Beliau berkata demikian di Mesyuarat Khas Forum Ekonomi Dunia (WEF) di Riyadh hari ini.
Delegasi Hamas ke Kaherah bincang gencatan senjata
Satu delegasi Hamas akan melawat Kaherah untuk rundingan yang bertujuan untuk mendapatkan gencatan senjata, pada Isnin.
37 juta tan serpihan runtuhan di Gaza - UNMAS
Pusingan konflik Palestin-Israel yang bermula pada Oktober 2023 telah meninggalkan kira-kira 37 juta tan serpihan runtuhan di Semenanjung Gaza.
WCK sambung misi bantuan di Gaza
World Central Kitchen (WCK) menyambung semula operasi di Semenanjung Gaza, pada Isnin.
Protes di universiti A.S tidak tunjuk tanda perlahan
Protes di universiti Amerika Syarikat tidak menunjukkan tanda perlahan pada hujung minggu dengan lebih banyak tangkapan di kampus dan pertempuran singkat antara penunjuk perasaan pro-Israel dan pro-Palestin di UCLA California.
Banjir ragut 76 nyawa di seluruh Kenya
Daerah Nairobi terjejas teruk akibat banjir dengan hampir 17,000 isi rumah dipindahkan.
Kerja pemasangan sistem projek ECRL dijangka bermula Mei depan
Kerja-kerja pemasangan di Laluan Rel Pantai Timur (ECRL) melibatkan pembinaan sistem elektrifikasi, semboyan dan telekomunikasi bagi pengoperasian kereta api penumpang dan kargo dijangka bermula Mei d
Kementerian Pengangkutan yakin ECRL siap Disember 2026, mula operasi Januari 2027 - Loke
Kementerian Pengangkutan yakin Laluan Rel Pantai Timur (ECRL) akan dapat disiapkan mengikut jadual pada Disember 2026 dan beroperasi bermula Januari 2027.
Kerajaan susun strategi perkukuh daya saing pelabuhan negara
Kerajaan telah menyusun strategi jangka masa pendek dan panjang bagi memperkukuhkan daya saing pelabuhan utama negara iaitu Pelabuhan Klang dan Pelabuhan Tanjung Pelepas.
Kelantan tiada masalah pengambilan tanah untuk lanjutkan ECRL ke Rantau Panjang
Kerajaan Kelantan tidak mempunyai sebarang masalah pengambilan tanah jika cadangan pelanjutan Laluan Rel Pantai Timur (ECRL) disambung sehingga Rantau Panjang dipersetujui kerajaan MADANI.
Kemajuan pembangunan projek ECRL di Terengganu melebihi 80 peratus
Kemajuan projek di negeri ini adalah yang terpantas dan mencatat peratusan tertinggi berbanding tiga negeri lain.
Isu sambung ECRL hingga Rantau Panjang telah dibincang dalam MTEN - Loke
Isu penyambungan jajaran Laluan Rel Pantai Timur (ECRL) hingga ke Rantau Panjang telah dibincangkan oleh kerajaan dalam mesyuarat Majlis Tindakan Ekonomi Negara (MTEN) baru-baru ini.
Kos pembinaan ECRL kekal pada RM50.27 bilion - Anthony Loke
Kos pembinaan Projek Laluan Rel Pantai Timur (ECRL) masih kekal pada RM50.27 bilion.
Kemajuan projek ECRL di empat negeri capai lebih 60 peratus
Darwis berkata kemajuan berkenaan setakat Februari lepas dan pembinaan projek ini berjalan lancar.
Projek ECRL berjaya capai penembusan 30 terowong
Tiga terowong tersebut adalah terowong Bentong 1 sepanjang 561 meter, terowong Kampung Lentang 1 (270 meter) dan terowong Kampung Lentang 2 (478 meter).
Projek ECRL ikut jadual, kini capai 62 peratus
Projek Laluan Rel Pantai Timur (ECRL) berjalan mengikut jadual dan kini sudah mencapai 62 peratus setakat Februari 2024.